Integrated Hybrid Power
Solution Delivered
What was delivered
- 70,000 L bulk fuel storage tank
- Variable-flow dispensing at 400, 600 and 800 L/min, with a dedicated heavy vehicle loading arm
- Self-powered hybrid system: Fuelfix ESU50 Battery Energy Storage System (BESS) and an 8kW solar array
- Fuel management system with RFID, including setup, monitoring and ongoing support for a large mobile and static fleet
- Remote site energy management
- Engineering, on-site commissioning, calibration and ongoing servicing
What are the operational benefits of the solution
- Estimated annual benefits, compared with a conventional 40kVA generator:
- About 20,800 to 26,000 L of diesel avoided
- Approx. 56–70 tonnes fewer CO₂ emissions
- About 219 tonnes fewer CO₂ emissions
- About 17 fewer major generator services
- Approx. $8,500 in maintenance labour avoided, at $500 per services
- About $45,760–$57,200 in fuel saved, at $2.20/L
Fewer refuelling and servicing activities means less vehicle movement on site and less exposure to higher-risk tasks for site personnel.
Estimates are based on the conventional generator baseline in the project brief. See how we measured this.
Current Performance

Efficient Dispensing

High Flow Rate

Reliable Power

No Dedicated Generator
Project Overview
ACJV needed high-volume fuel storage and fast refuelling for construction in the Central-West Orana Renewable Energy Zone (REZ), NSW. Fuelfix delivered a self-powered fuel facility: a 70,000 L tank and high-flow dispensing system run on solar and battery power, with no standalone generator.
In its first five to six weeks of operation, the facility has dispensed an average of about 8,000 L a day, and the solar array has generated more than the dispensing load needs.
This isn’t only a transmission-project problem. Mine sites, civil projects and depots that need fuel on site face the same issue: a generator running around the clock just to power the pumps burns diesel and needs regular servicing.

Challenges
ACJV needed fuel on site fast, while permanent fuel infrastructure was still being built. A conventional set-up would have added a dedicated 40kVA diesel generator to power the facility, using about 400–500 L of diesel a week and needing a service every 21 days.
On this project, the key challenges were:
- Getting a high-volume fuel facility on site within three weeks of leaving Fuelfix’s facility, so operations could start
- Storing enough fuel for light vehicles, service trucks and heavy construction equipment
- Refuelling heavy equipment quickly, to cut the time it spends off the job
- Powering the facility without a generator’s fuel, servicing and logistics

What were the project objectives?
- Reliability and resilience: dependable, self-powered fuel supply for continuous operation in a remote environment
- Operational efficiency: high-flow refuelling with minimal equipment downtime, site intervention and supporting logistics
- Low maintenance and autonomy: minimal servicing, with enough battery to keep operating when solar generation is limited
- Lower whole-of-life cost: no dedicated generator, and none of its fuel, servicing and maintenance
Why did Select Plant Hire choose Fuelfix?
ACJV wanted a supplier who could deliver high-volume storage and fast dispensing for a remote site with minimal site support and have it operating within three weeks of leaving Fuelfix’s facility. Fuelfix brought experience with hybrid power on remote sites, along with in-house engineering and commissioning support.
Solution
Fuelfix delivered storage, dispensing, power and fuel management as one integrated package:
70,000 L bulk fuel storage tank:
holds enough fuel for sustained construction operations and reduces how often bulk fuel has to be replenished.High-flow dispensing:
variable flow rates of 400, 600 and 800 L/min, including a dedicated heavy vehicle loading arm, so large equipment refuels quickly.Solar and battery power:
an 8kW solar array and a Fuelfix ESU50 BESS power the dispensing system. The array generates 15–20 kWh on a typical day, enough to support more than 48,000 L of dispensing a day.Fuel management system:
RFID technology records every fill by vehicle or equipment, giving accurate transaction data and easy use for operators.- At current site consumption, the battery provides about 15 days of standby operation without solar input, which covers low-sun periods and bad weather.

Delivery and commissioning
The brief was to have the facility on site within three weeks of leaving Fuelfix’s facility, so operations could start while permanent fuel infrastructure was being set up.
It was delivered through a staged rollout, with commissioning completed in September 2026.
Results
In its first five to six weeks of operation, the facility has dispensed an average of about 8,000 L of fuel a day with no dedicated generator.
What was the operational impact during the reporting period?
- Dispensed an average of about 8,000 L of fuel a day from 70,000 L of on-site storage
- Refuelled heavy equipment at up to 800 L/min
- Powered the facility from solar and battery, with no dedicated 40kVA generator
- Generated more solar energy each day than the dispensing load needed
- Recorded every fill by RFID, giving accurate fuel data across the fleet
What are the safety and environmental benefits during the reporting period?
- Fewer generator refuelling activities and less fuel handling
- Fewer planned generator services, so fewer contractor visits
- Lower emissions from generator operation
Annualised outlook
The conventional generator was never installed, so these figures are estimated against the baseline in the project brief: a 40kVA generator using 400–500 L of diesel a week, serviced every 21 days.

Project Feedback
"Fuelfix assisted us with the setup of a temporary self-powered servuce truck dispensing solution that needed to power itself . The Fuelfix team worked closely with us to understand our requirements and delivered a solution that met what we needed.
Within just three weeks, Fuelfix had a full system on the ground and ready for commissioning. The entire process was managed professionally, with clear communication and a strong focus on meeting our project deadlines.
Since commissioning, the system has performed exceptionally well and providing reliable operation - it is incredibly impressive as the system is 100% solar powered.
A big thank you to the team at Fuelfix for their expertise, responsiveness, and commitment to delivering a quality solution. We would have no hesitation in recommending Fuelfix for temporary or permanent fuel infrastructure projects."
Project Manager - ACJV
Trusted to Deliver Integrated Fuel and Energy Solutions
This project shows how Fuelfix combines fuel storage, high-flow dispensing, solar and battery storage in one facility that runs without a dedicated generator. In line with our Two Pathways, One Goal Strategy, we develop practical energy solutions that reduce operating costs and emissions without compromising reliability.
See another Fuelfix project at ORANA in our Select Plant Hire case study, or discover how hybrid power systems compare to traditional diesel generators.
Need fuel on site fast, without a generator? Planning a remote site or construction project? Talk to our team about a self-powered fuel solution sized to your fleet and site.
Key services provided

Bulk fuel storage & high flow-dispensing
Fuel Management System
Battery Energy Storage Systems (BESS)
Engineering, commissioning and technical support
How did we measure the performance results?
The savings figures in this case study are based on actual site operating data combined with industry-standard assumptions about generator fuel consumption and efficiency. While actual results may vary, this method gives a reasonable representation of the fuel, emissions and operational savings attributable to the hybrid power system.
How we measured the performance results
Current performance (dispensing volume, solar generation and battery standby) is based on actual site operating data and system specifications for the first five to six weeks of operation from 24 September 2026.
Annual savings are estimated against a conventional-generator baseline from the project brief, because that generator was never installed.
Baseline
A conventional deployment would have used a dedicated 40kVA diesel generator running 24/7, typically at idle, using about 400–500 L of diesel a week. Over a year, that is about 8,760 operating hours.
Major service
Every 500 generator operating hours, about every 21 days of continuous running, or about 17 services a year.
Diesel and emissions
Emissions factor ≈ 2.7 kg CO₂ per litre (69.9 kg CO₂/GJ × 38.6 GJ/kL - DCCEEW, National Greenhouse Accounts Factors 2025, Table 8).
Fuel and servicing costs
Diesel at $2.20/L and maintenance labour at $500 per service (labour only, parts excluded).
Can a fuel facility run without a diesel generator?
Yes. At the ACJV Orana site, an 8kW solar array and a Fuelfix ESU50 battery energy storage system power a 70,000 L fuel facility, with no dedicated generator. In its first five to six weeks, it has dispensed an average of about 8,000 L of fuel a day.
How fast can a self-powered fuel facility dispense fuel?
The ACJV facility dispenses at 400, 600 or 800 L/min, and a dedicated loading arm lets heavy vehicles and large equipment refuel quickly.
What happens if there is little sun?
At current site consumption, the battery provides about 15 days of standby operation without solar input.
How is fuel use tracked on a large site?
An RFID fuel management system records every fill by vehicle or equipment, giving accurate transaction data for a large mobile and static fleet. Fuelfix sets up, monitors and supports the system.
How quickly can a fuel facility be set up on a remote site?
The ACJV facility was brought on site within three weeks of leaving Fuelfix’s facility, so operations could start while permanent fuel infrastructure was being set up.
Does this apply to mine sites and civil projects?
Yes. Any remote site that needs fuel on site and would otherwise run a generator to power the pumps faces the same issue. Our solution supplied for the Lotus Creek wind farm project shows the same hybrid approach at a remote construction site in Central Queensland.